NMT has successfully completed a precision tower crane dismantle up North this week, showcasing our technical expertise and planning that defines our approach to complex lifting operations.

Using our 300-tonne Liebherr L1300-6.2 mobile crane configured with a 38.5-metre luffer, the team safely removed the tower crane in a tightly controlled environment. The operation required overcoming multiple challenges including restricted site access, significant height considerations, and the unpredictable winter weather conditions typical of the northern region.

“This is exactly the type of operation where experience and preparation make all the difference,” said JD Ambridge, Joint Managing Director of NMT.

“Tower crane dismantles are never straightforward, but when you add restricted access and challenging weather into the equation, every detail of your lift plan becomes critical. Our team executed this flawlessly through meticulous planning, detailed rigging preparation, and clear communication at every stage.”

The operation remained smooth and fully compliant from start to finish, with safety protocols maintained throughout despite the demanding site conditions.

This successful dismantle is another demonstration of our capability, reliability, and experience that customers across the UK rely to deliver for complex dismantles and major lifting operations.

Here’s a reminder of just some of what we do:

  • Complex tower crane dismantles in restricted and challenging environments
  • Heavy lift operations using our fleet of mobile cranes including the Liebherr L1300-6.2
  • Precise lift planning with detailed engineering and risk assessment
  • Nationwide coverage with local expertise and knowledge
  • All-weather operations with contingency planning for adverse conditions

Whether it’s a tower crane dismantle in confined urban spaces, a heavy lift on a remote site, or a time-critical operation requiring precision planning, NMT brings the same level of technical expertise and operational excellence to every project.

From the initial site survey through to final handover, we ensure that every lift is engineered for safety, efficiency, and complete compliance with all relevant regulations.

How To Build A Realistic Programme When You Need A Crane

Posted in UncategorizedLeave a Comment on How To Build A Realistic Programme When You Need A Crane

Cranes are not the same as hiring a photographer for the day. It needs far more planning taking into consideration safety, timing, access, permits. Our team at NMT Crane Hire can help out with an entire range of projects with our main ones including Film & TV and large scale industrial developments. With the help of some crane management you can expect a process that works in your favour the entire time. 

Why Is A Plan Necessary

In some work schedules and plans, you can be flexible and adjust times, people and more to suit a better idea. When a crane is involved, it eliminates that freedom. With good preparation up front, you gain much more certainty. You’re ready for inspections, permits and access checks, and you’re in a far better position to handle last-minute changes or cancellations.

Without A Plan You Can Expect The Following

Cranes turning up with nothing ready to lift
The crane and crew are on site, but the load isn’t prepared or the area isn’t cleared, so you’re paying for them to wait.

Crane can’t get in or set up where you’d planned
Parked cars, street furniture, tight corners or weak ground mean the crane can’t reach the agreed position.

Booked crane too small or can’t reach the load
The weight or radius was guessed, so the crane on the day isn’t safe to make the lift.

Lifts cancelled due to missing permits or parking suspensions
Road closures, TM, or bay suspensions haven’t been approved, so the job is stopped before you even start.

Trades and deliveries clashing with the crane’s working area
Other contractors are working or storing materials in the lift zone, forcing everything to be moved at the last minute.

Operator refusing to lift because paperwork isn’t in place
No agreed lift plan, RAMS or Appointed Person means the operator can’t legally or safely go ahead.

Rebooked cranes, extra visits and standing time charges
The lift has to be aborted and rearranged, adding more hire costs, more TM and more disruption to your programme.

What Steps Your Planning Should Include

There are many different procedures and steps you could include to make an efficient plan but sometimes quantity isn't quality. In an instance where a crane is involved, there may be some that you hadn't already thought of, here are them:

1. Confirm what you’re lifting and when

Lock in the basics first.

  • What are you lifting
  • How heavy is it and how big is it
  • How many lifts will there be and on which days
    This lets the crane team choose the right crane and configuration instead of guessing.

2. Map out access and crane set up

Plan how the crane and the load will get in and out.

  • Vehicle routes in and out of site
  • Where the crane will stand and slew
  • Any tight corners, low bridges or height limits
    Photos, videos and simple sketches are really useful here.

3. Arrange a site visit and lift plan

For anything more than a very simple lift, schedule:

  • A site visit from the crane company
  • A formal lift plan and RAMS
    This is where ground conditions, radius, obstacles and safe working areas are nailed down.

4. Build permits and traffic management into your dates

If you are near a road or public space, add time for:

  • Road closures or lane closures
  • Parking suspensions and access permissions
  • Traffic management booking and approvals
    These all have lead times, so they need to sit in your programme, not as an afterthought.

5. Coordinate trades and deliveries around the lift

Make sure other activity does not clash with the crane.

  • Keep the lift zone clear of scaffolding, roofers and other trades
  • Time deliveries so loads arrive ready to be lifted
  • Avoid booking other noisy or disruptive works at the same time
    The crane should be the focus during the lift window, not fighting for space.

6. Allow for weather and backup dates

Cranes and high winds do not mix.

  • Identify critical lifts that may need a backup day
  • Keep some flexibility in your programme for weather delays
  • Agree how and when decisions will be made
    This keeps everyone calm if the forecast changes.

7. Confirm who is in charge on the day

Finally, be clear about roles.

  • Who is the main contact for the crane crew
  • Who is the Appointed Person if it is a contract lift
  • Who can make decisions if something changes
    Good communication means fewer surprises once the crane is on the clock.

Contact Us & Get Planning Today

Get in contact with our team at NMT Crane Hire for more support and understanding of the required planning processes when a crane is involved in your projects.

NMT Crane Hire expands heavy storage solutions across Birmingham and Bedford

Posted in News MediaTagged , Leave a Comment on NMT Crane Hire expands heavy storage solutions across Birmingham and Bedford

As demand for reliable heavy storage and logistics support continues to grow, NMT is proud to offer flexible, secure storage solutions from its two strategically located depots in Birmingham and Bedford.

NMT has developed a strong reputation for providing dependable, well-managed storage space tailored to the needs of the construction, engineering, and lifting industries.

At our Bedford depot, we are already supporting a number of clients with long and short-term storage requirements. And with our expansive yard, there is more room to grow.

One client has enlisted our help on their #modular buildings on a long-term lease. However, with additional capacity now available, we’re inviting businesses looking for secure, accessible, and professionally managed storage to get in touch and discuss their needs.

James ‘JD’ Ambridge Ambridge, Joint Managing Director at NMT Crane Hire, said: “Following the success of a partnership in #Birmingham, we’ve seen growing demand for dependable heavy storage solutions.

“Our Bedford site offers significant capacity and the same level of professionalism and accessibility that clients have come to expect from NMT. We’re ready to support more businesses with flexible space and seamless logistics support.”

With over 40 years of experience in the crane hire and heavy logistics sector, NMT combines operational expertise with a commitment to customer service – ensuring every solution, whether crane hire or storage, meets the highest standards of reliability and efficiency.

For enquiries about storage opportunities at either our Birmingham or Bedford depots, contact the NMT team today hiredesk@nmtcranes.co.uk